Skip to main content

WPD | VRP | Avra Valley Mining & Development

VRP Site

I-10 Avra Valley Mining & Development, LLC

Revised On: Mar. 11th, 2025 - 01:04 pm

Location: 

  • 7755 and 7851 W. Avra Valley Road, Marana, AZ 

Acceptance Into Voluntary Remediation Program (VRP):

  • Oct. 25, 2023

Contaminants of Concern (COCs):

  • Arsenic
  • Cadmium 
  • Copper
  • Lead

Affected Media:

  • Soil

What are My Health Risks:

  • For Soil | There is little to no health risk unless there is contact with skin or ingestion of contaminated soil

Site Summary:

  • Application submitted Oct. 5, 2023
  • VRP accepted the application on Oct. 25, 2023
  • The Volunteer submitted a Work Plan that included a Sampling and Analysis Plan (SAP) on June 12, 2024
  • The VRP requested revisions to the Work Plan on July 18, 2024
  • The Volunteer submitted a Revised Work Plan on Aug. 16, 2024
  • The VRP requested revisions to the Work Plan on Sept. 9, 2024
  • The Volunteer submitted a Revised Work Plan on Feb. 24, 2025
  • The VRP issued a Preliminary Approval of the Work Plan on March 3, 2025
  • The Work Plan will be available for comment March 10 – April 10, 2025 | View Public Notice >

Project Manager
P: 602-771-2256
Email >


VRP Unit Manager
P: 602-771-1612
Email >