Skip to main content

AQD | Minerals Research, Inc. (MI) | Permit of Interest

Air Quality Site/Facility of Interest

Minerals Research, Inc.

Revised On: Nov. 1st, 2024 - 06:37 pm

This Site/Facility of Interest is an online resource that provides interested parties easy access to information about the Minerals Research, Inc. (MRI) facility.

Permitting

On Oct. 31, 2023, ADEQ received an Individual (Class II) Air Quality Permit Application from MRI for the operation of its Cottonwood facility and deemed the application complete on Nov. 14, 2023 (see following Background and Documents for details).

ADEQ is reviewing MRI’s application and expects to make proposed air quality permit documents available to the public for review and comment during the first quarter of 2025. ADEQ’s air quality permitting process for an Individual Air Quality Permit involves a comprehensive review of emissions calculations and associated air dispersion modeling and the development of a draft permit and technical supporting document. ADEQ will make these permitting documents available for public comment, and conduct both an informal community meeting and a formal public hearing for the draft air quality permit prior to making a final permit decision.

  • Air Quality Permit Application | View >

Other ADEQ Activities

ADEQ Ambient Air Quality Monitoring

At a community meeting ADEQ conducted on Dec. 13, 2023, in partnership with the City of Cottonwood, ADEQ committed to conduct ambient air quality monitoring for particulate matter and heavy metals in the vicinity of MRI’s facility. ADEQ set up ambient air quality monitoring equipment at the two locations discussed at the community meeting — the Cottonwood Kid’s Park and the Veterans of Foreign Wars — and trained local volunteers on how to assist ADEQ with the project. ADEQ extends its sincere gratitude to these dedicated volunteers whose assistance was invaluable to this monitoring effort. Ambient air quality monitoring commenced on Feb. 15, 2024 and ended on June 9, 2024.

  • Cottonwood Air Quality Monitoring Report 2024 | View >

Based on the particulate matter analysis, which indicated elevated levels of lead at the VFW site, ADEQ plans to conduct an additional three months of Lead sampling in the near future.

ADEQ will provide all data to the Arizona Department of Health Services (ADHS) as they conduct a health consultation. Results from the ADHS health consultation are expected in late 2024 or early 2025. 

ADEQ Preliminary Investigation (PI)

ADEQ has initiated a PI under our state Water Quality Assurance Revolving Fund (WQARF) program | Learn More >

The PI is focused on potential impacts to soil and groundwater associated with the slag pile located at the MRI facility and the former smelter operations in the surrounding area. In addition to reviewing available historical reports and environmental data regarding operations and activities in the area of the MRI facility, the PI includes collecting soil and groundwater samples in the field for laboratory testing. During March and April, ADEQ collected and tested soil and groundwater samples from properties and wells that allowed ADEQ access to conduct sampling. ADEQ is assessing this environmental data to determine if additional sampling is necessary to complete the PI. ADEQ anticipates that the PI, including data evaluation, will be completed by August 2024, and the final report could be made available by late summer 2024. Following completion of the PI, ADEQ will determine what, if any, additional action may be warranted. ADEQ will share all data collected for the PI with ADHS and publish the final PI report (including all data) on this webpage.